ABSTRACT
EVMWD’s Board of Directors’ meeting
held on September 26, 2002 significantly changed the direction of the
LEAPS Project. This article sets the stage for the meeting, reports
on just what was said using tape recorded transcripts (i.e. the “voices
from the past”) and concludes with critical analysis of why
the results of this meeting are still relevant today.
INTRODUCTION
By mid-2002, Enron Corporation had completely withdrawn from the LEAPS
Project due to overwhelming corporate problems that led to its bankruptcy.
That left only EVMWD and Nevada Hydro to move the LEAPS Project forward.
This posed a serious problem
because EVMWD’s position, as expressed
in the 1997 Development
Agreement (pdf) with Nevada Hydro, was that:
District [EVMWD] supports the continued development of the Project
as in the public interest but does not wish to spend the remaining
funds required to obtain the FERC License and to construct and operate
the Project.
Further:
Company [Nevada Hydro] will provide all necessary funding and will
pay all expenses and costs to complete and submit the FERC License
application to obtain the FERC License and to obtain Related Entitlements.
The problem was that Nevada
Hydro did not have sufficient funds to fulfill it’s contractual commitment. That’s one of the
principal reasons why Nevada Hydro had previously worked to find an
organization like Enron, with deep pockets, to participate in the LEAPS
Project. In fact, Enron was indeed “paying the bills” before
they abandoned the project and went bankrupt.
NEVADA HYDRO’S PROPOSAL
The absence of Enron left
Nevada Hydro in a very serious situation. And by mid-2002 there was
a very large anticipated expenditure (several
hundred thousand dollars to retain Washington lobbyists) that was considered
necessary to move the LEAPS Project forward. While there’s much
more that will be said about this expenditure later, the pressing problem
that will be addressed at this point is “Where was the money
to come from?”
Nevada Hydro’s answer to this question was that EVMWD should
make the payment and that Nevada Hydro would “guarantee” repayment.
Specifically, Nevada Hydro’s President, Peter Lewandowski, proposed
to Ron Young, General Manager of EVMWD, in a letter dated July 31,
2002 that:
District [EVMWD] costs
incurred to retain Washington lobbyists addressing the issue of
multiple use of public lands [specifically
the Cleveland National Forest for both recreation and for a power
line right-of-way] would, therefore constitute a legitimate
reimbursable expenditure in accordance with our agreement. THNC
[The Nevada Hydro Company] commits
to reimburse the District for 100 percent of those costs. [Underlined
for emphasis]
The problem here for EVMWD
was that Nevada Hydro did not plan to back their “commitment” with any collateral. If EVMWD accepted
there terms and made the payment, it would be in the form of an unsecured loan to Nevada Hydro. In effect, EVMWD’s unsuspecting rate-payers
would be assuming the financial risk for the LEAPS Project while Nevada
Hydro would gain the principal financial benefits if the Project were
successful.
THE SEPTEMBER 26, 2006 BOARD MEETING
This set the stage for the
September 26, 2002 EVMWD Board of Directors meeting. Action on the
Nevada Hydro proposal to finance the payments
to the Washington lobbyists was the main topic on the agenda. Four
of the five directors were present; Phil Williams, President, Kristine
Anderson, Vice President, Gary Kelley, and George Alongi. Also present
was Ronald Young, General Manager of EVMWD. By the time of the meeting,
all of these individuals, except Director Alongi, were inclined to
accept Nevada Hydro’s proposal. As you’ll see, there was
a spirited and very informative debate at this meeting. But, did it
have any effect on the outcome?
The following is an audio transcription of the discussion that was
made from a tape recording that is retained by EVMWD. These are the
actual Voices from the Past:
YOUNG – The staff is recommending approval of two agreements
with lobby and consulting firms regarding LEAPS. The cost of these
contracts will be fully reimbursed by NHC [Nevada Hydro
Company], so
no financial impact on the District. The work they are going
to be involved in is the legislative work in the bill that is
being moved
through. It has been introduced in ( to) Congress, and we will
be moving ahead. Our Congressman, Darrell Issa, has introduced
that. That’s
really what this is all about and being able to function inside the
beltway, if you will, with the Congress, with the various committees;
the Energy Committee, the Natural Resources Committee, and the Public
Works - and all that to be able to navigate the labyrinth of approvals.
…………… .
WILLIAMS - …. .
Now we have time for comments.
ALONGI – We are right back where we were before, when this wasn’t
supposed to cost the District any money. We have a developer [Nevada
Hydro] out there that doesn’t have financing in place. We have
a representative [Director Phil Williams] who has now
changed his mind and wants to put the power lines through the
[Cleveland] National Forest,
which he didn’t commit himself before. So, now we have someone
in Congress [Darrell Issa] changing his mind. But here
we sit on the Board, and we’re going to agree to pay $10,000 a month to a consultant
to do the work that the Hydro Company people should be doing, not us.
We’re supposed to be riding free here. We are supposed to be
the guys who are supposed to reap the benefits. They pay, we reap the
benefits. And still, there is no money, there’s no bonds, there’s
no guarantees, there’s nothing out there except their word that
they’re going to reimburse us. That means absolutely nothing.
I could tell you that I am going to reimburse you for a million dollars.
It doesn’t mean that you’re going to get it. And here we
are. We’re going to spend another $10,000 a month to do some
more studies on this hydro deal through legislative. Even the agreements
[the terms in the 1997 Agreement with Nevada Hydro] don’t mention
him [the person responsible at Nevada Hydro]. It’s all on us.
I just can’t believe you people [the other Directors] continue
to do this. We’re spending a bunch of money now on a topo map
that’s going to benefit them [Nevada Hydro] if
they move forward with their project. It just goes on and on
and on. We just spent $30,000
for the study to find out what benefits we’re going to get out
of it. I mean, how much more money do you people want to spend on this
thing. Where are these people’s dollars? Where are they? Where’s
the banks? Where’s any kind of commitment from the people saying; ”Here,
I have a guarantee for $500,000 to do this project. You have to get
it approved for me.” We don’t have any of that and yet
we keep spending money. That’s it. Thank you.
WILLIAMS – Let me
ask this real quick. Have we heard from the Hydro Company? Have
they come close to a finance group yet?
YOUNG – They continue to work on that. I believe that they are
very close but, of course, their discussions are their business deals
and their contracts, so I’m not, if you will, privy to the
details. I have met with the various potential investors and every
different
entity that has come to the District to look at our facilities. And
our involvement to the projects has been very positive about their
interest. I guess I can only report that things look very positive
and we are moving ahead. We have a meeting in the near future to
meet with the fire service about these issues. So, things are continuing
ahead at a regular pace, an anticipated pace. The developer is continuing
to make their progress reports or quota reports to the FERC. So,
we
can publish those reports. So, they are on schedule and everything
looks like it is moving ahead at this point in time.
ALONGI – There is still no, in all due respect to our managers,
there is nothing in writing from any investor, any investor. If they
[Nevada
Hydro] would send me a letter from an investor saying they’re
interested in the project, I might relax a little bit. But they don’t
even have any type of commitment to that effect. It’s all word
to mouth. He said this - they said that. We met with them - they told
us this. There’s no written commitment. We wouldn’t move
on a project if we didn’t have a written commitment from the
developer. What’s he going to do? How is he going to pay his
fees to us? We wouldn’t move forward. Why are we moving forward
on something that’s in the millions and we don’t know what’s
happening? We haven’t a clue as to what these people are doing
out there. Not a clue. And, I think before we move ahead and spend
any more of the District’s money, we should at least try to get
a commitment from them, a letter from them, from some person or some
agency saying “Yes, we are very interested in it, in this investment,
and we are negotiating it.” But we have nothing. I mean – please.
WILLIAMS – Well, the concern that I have, and maybe you can
answer this Mr. Young, I’ve been reading the papers and that
our project [LEAPS],
or our proposed project, has now become a potential alternative
to SDG&E, in which it would be SDG&E’s line.
And the concern that Director Anderson has had along, and the concern
that previous directors have always said that if we don’t put
this line in, then potentially someone else will put the line in. And
if they put it in, then our District and our community receives nothing – as
opposed to if we take the bull by the horns and actually lead the charge.
And it’s my assumption by hiring these consultants, I understand
that Washington DC can’t come out and say that this is the Elsinore
Valley line. I understand some of the legal maneuvering and the political
maneuvering that‘s going on. These people are there to
protect our rights if the project does go forward. Or if the
project goes
forward, is that what they are there to lobby for - and also
the successful
routing?
YOUNG – I think that’s
absolutely correct. And the implication here, I think is very strong.
When EVMWD enters these contracts, then
it is EVMWD that is the proponent of this line, is the proponent
of the LEAPS project. When this initially started out, I agreed with
congress
needing to have a generic description of the facilities. But the
recent newspaper articles make it very clear, as does the actions
here, and
actions speak louder than words. Our action here is to say that this
is our project. This is our project that we are lobbying for. We
are moving ahead, not just with the transmission lines, but with
the LEAPS
Pump Storage project.
We’ve seen the talking points that very clearly describe (outline)
everything that has been described in the applications to the FERC
that this is a project that will benefit 250,000 people by providing
peak power during - when the time power is going to be short. There
would be potential brown-outs. We see this as a green power project
with using gravity as our fuel source instead of using hydrocarbons
and coal and other things that put pollutants in the air when you produce
this power. So, you see all the positive aspects. This is our action
to move ahead. I think the corrections we made to the agreement [to
make a minor change to the termination date], the modifications are
very good ones. I think we should continue. And as potential investors
become available, if any one of the directors would like to meet with
these investors, shake their hands, see their presentations, understand
what questions they’re asking, we would be more that happy
to make those arrangements so that we could move ahead and get a
better
look at the project.
Right now, we have a committee
[an ad
hoc committee] of the Board that we’re keeping apprised
at the highest level.[The ad hoc committee lasted for
five years and succeeded in keeping knowledge
of the LEAPS Project out of reach of the public.] But if
other directors are interested, we could do that.
WILLIAMS – Are they
[Nevada
Hydro] at the point were they are willing to do that?
YOUNG – We should
probably make that schedule available to the other directors.
At this point the vote to approve the staff recommendation to retain
the Washington lobbyists was taken. The measure passed by a margin
of 3 to 1, with Director Alongi being the only dissenter. So, the discussion
had no impact on the outcome of the vote.
CRITICAL ANALYSIS OF THE BOARD MEETING
In retrospect, it is striking
at how naïve Ron Young was about
progress being made by Nevada Hydro to secure an investor. Even now,
five years latter, a committed investor is no closer at hand. In fact,
the outlook is substantially more problematic (see The
Case for including Expenditures for LEAPS in the EVMWD FY 2007-2008
Budget). Very recently,
EVMWD released yet another story that the investment banking firm of
Morgan Stanley may have an interest in backing LEAPS. But, like all
previous investment possibilities, no commitments have been secured
in writing.
It is also very striking
how bullish both Mr. Young and Director Williams were about “taking the bull by the horns” and “actions
speak louder than words” expressing a gung ho attitude that was
not supported by facts. They can be specifically faulted for accepting
the “talking points” about the LEAPS Project hook, line
and sinker. That’s because Nevada Hydro, an organization that
would clearly benefit financially if the LEAPS Project were built,
influenced these talking points.
While naivety many be excusable, there can be no excuse for Young
making the strong statement that:
The cost of these contracts will be fully reimbursed by Nevada Hydro,
so no impact to the District.
without addressing or even
mentioning Director Alongi’s concern
that Nevada Hydro was proposing an unsecured loan!
One wonders what EVMWD’s lawyer, John Brown, might have advised
Mr. Young and the Directors about the risks of accepting an unsecured
loan from an organization that is known to be short on cash and other
resources. If Mr. Brown didn’t raise lots of red flags, a good
case could be made that he should be fired. If he did, an even better
case could be made that Mr. Young should be fired.
In this regard, things don’t
look particularly good for attorney Brown who, according to Director
Alongi, attended the Board meeting
but said nothing about the unsecured aspect of the proposed loan to
Nevada Hydro.
Even without having the
lawyer’s warning, Mr. Young should have
seen the serious risks involved in Nevada Hydro’s proposal. After
all, he is being paid well as a senior executive to look out for the
best interests of EVMWD’s rate-payers.
REQUEST FOR INDICTMENT OF DIRECTORS
About a half year after the September 26, 2002 Board meeting, a group
of residents from the community of Rancho Capistrano prepared and
submitted a legal complaint to the Riverside County District Attorney’s
Office requesting the indictment of the three Directors who approved
the risky expenditures on the LEAPS Project (see the Rate-payers’ Complaint).
The basis of the complaint is that:
On September 26, 2002,
the EVMWD broke California State Law when they carried a motion to
implement
two Lobbyist Agreements ($20,000 per
month, for up to one year), relative to the Lake Elsinore Advanced
Pump Storage Project (LEAPS). In California, it is illegal to make
risky, unsecured investments with public funds (See Government Code
Sections 53600, 53601, and 53601m). The State Code requires that “local
agencies” investing public funds are fiduciaries subject to the “prudent
investor standard” (see Section 53600.3). The guidelines set
fourth by government code clearly state the “primary” objective
is the safety of the principal (see Section 53600.5).
This complaint also requested
that the District Attorney depose the staff and Board of Directors
of the EVMWD, in order to investigate
the possibilities associated with EVMWD funds being put forth to Congressman
Issa’s political campaign for reasons that are covered in the
Rate-payers’ Complaint.
Basically, it appears that Congressman Issa timed his statement in
Congress about the value of the LEAPS Project to coincide within days
of the approval action taken by the EVMWD Board on September 26, 2002.
It may be presumed that he also was instrumental in guiding EVMWD to
the two Washington lobbyist firms that each received payments from
the District of $10,000 per month for a year. A total of $240,166 was
actually paid by the District to these firms.
One of these firms known as ASG (Alexander Strategy Group) had close
ties to the discredited lobbyist Jack Abramoff, who is now under Federal
indictment. ASG closed down in the wake of the recent (K-Street) lobbyist
scandal in Washington, DC.
While it is entirely possible
that some of monies paid by EVMWD to ASG and the other lobbyist firm
(Ryan, Phillips, Utrecht & MacKinnon)
ended up in Congressman Issa’s campaign funds, there is no evidence
yet that this is the case.
About a half year after the complaint was filed with Riverside District
Attorney, Grover Trask, he responded with a letter that stated:
The propriety of the
LEAPS project and the hiring of lobbyists is a political/policy
matter
to be decided by the Water District Board.
Disagreement with the Board’s decision should be handled
by the political process or civil lawsuits. A criminal investigation
does
not appear appropriate at this time.
POST SCRIPT
The residents of Rancho Capistrano, who initiated the complaint did
not have the financial resources to proceed with a civil lawsuit. Lacking
the discovery process that a lawsuit could provide, this matter remains
unresolved.
The District Attorney who
wrote the letter, Grover Trask, is now an employee of the law firm
(Best, Best & Krieger or, simply BB&K)
that currently represents EVMWD and has represented them for decades.
So, he is now an associate of attorney John Brown, who was mentioned
above in the CRITICAL ANALYSIS.
The Enron Manager, Rod Baknody,
who coordinated the LEAPS Project before Enron went bankrupt has
recently re-surfaced as a representative
of Nevada Hydro. He attended a Board of Director’s Study Session
at EVMWD on behalf of Nevada Hydro on June 20, 2007.
The action taken on September
26, 2002 served as a subsequent guiding principle in the relationship
between EVMWD and Nevada Hydro. Since
then, not only has EVMWD paid the $240,000 in lobbyists’ fees,
but a total of approximately $2 million on behalf of Nevada Hydro – all
as unsecured loans. This reckless use of rate-payers’ funds continues
to the present.
Further, a substantial portion
of the $2 million has been consumed by fees that were paid directly
to EVMWD’s law firm, BB&K.
As a result, BB&K now has a substantial vested interest in outcome
of the LEAPS Project. For this reason, it would be prudent for EVMWD
to drop BB&K as their general counsel and limit their involvement
only to LEAPS matters.
However, there is no known
action on this front by the present Board of Directors. Rather, there
is a growing concern that EVMWD may take
some sleazy final action, like supporting Nevada Hydro’s effort
to build only the power lines through the Cleveland National Forest.
While this might help to recover the unsecured loans made to Nevada
Hydro, it would also expose EVMWD to major lawsuits from residents
living near the power lines who would argue that their property values
were seriously diminished by EVMWD’s wonton action. They would
take the position that EVMWD has no business supporting the construction
of power lines other than to make up for a grave error in judgment
that EVMWD’s Board of Directors made on September 26, 2002.
While Nevada Hydro has yet
to pay back a single penny of the unsecured loans, they did manage
to “scrape together” about $60,000
to contribute to the 2006 election campaigns of three Director candidates
who were supportive of the LEAPS Project or its associated power lines.
Their substantial campaign contributions were laundered through a Political
Action Committee (PAC) located outside of Sacramento. Presumably, this
was done in hopes that the opponents of the LEAPS Project would not
notice the questionable origin of the funds. Fortunately, this sorry
matter was exposed by the press (see Valley
News and The Californian).