California Energy Commission June 13, 2007
Dockets Office, MS-4
Re: Docket No. 06-IEP-1F
1516 Ninth Street
Sacramento, CA 95814-5512
Subject: Lake Elsinore Advanced
Pumped Storage (LEAPS) & CEC Corridor
Planning Efforts
Reference: Docket No. 06-IEP-1F
2007 IEPR -Transmission
Dear Ms. White;
On May 14, 2007, The Nevada Hydro Company (TNHC) presented the LEAPS project
at the Joint Committee Workshop on In-state and Interstate Transmission and
Potential In-State Corridors. I just reviewed the TNHC presentation and the
transcript from the Workshop, and I have substantial concerns regarding the
accuracy and veracity of some of the LEAPS project information that was provided
by TNHC. In the paragraphs below, I specifically address these inaccuracies
and deficiencies in the same order as the TNHC presentation. My comments also
address inaccuracies in the testimony given by Mr. Wait during the LEAPS presentation.
I trust that the CEC will find this information useful in determining whether
or not to include LEAPS in any draft Corridor plan that is developed.
FROM PAGE 2 OF THE TNHC PRESENTATION:
“ TE/VS Interconnect functions as stand-alone reliability solution to San
Diego”
FALSE. The CAISO specifically found that the TE/VS component of LEAPS
is “not needed to solve any reliability problem” [May 1,
2007 CAISO comments in response to FERC’s order on Rate Request].
In fact, CAISO has also stated that “In general there are no reliability
concerns with the [LEAPS-TE/VS] project mainly thanks to the mitigating
effect of the Sun Path Project…” [from the August 31, 2006
CAISO Staff Memo to CAISO Board of Governors]. In other words, LEAPS-TE/VS
potentially causes reliability problems that can be avoided by implementation
of Sun Path. This position is also echoed in the Final Environmental
Impact Statement (EIS) document prepared by FERC for the LEAPS Project.
The truth is that CAISO has only evaluated the TE/VS component of the
LEAPS project in conjunction with the Sunrise Powerlink and the IID Green
Path project (together known to as Sun Path) and the Tehachapi project,
and has not conducted a detailed, stand-alone assessment of the LEAPS-TE/VS
project.
“500 MW of renewable storage…”
INCORRECT, INACCURATE, AND MISLEADING. For LEAPS to provide storage of
renewable energy, prior arrangements must be made to directly connect
LEAPS with renewable power sources. For example, LADWP is making arrangements
to exclusively transport Tehachapi wind power to operate their Castaic
pumped storage power plant, so it is legitimately claimed that the
Castaic Power Plant provides renewable energy storage (see testimony
re the LA Tehachapi Transmission Project and the May 14, 2007 CEC Corridor
Workshop). No such arrangements have ever been made for LEAPS, as evidenced
by the Project EIS (January, 2007) and all other reports prepared pursuant
to CARTS, CSRTP, STEP, TCSG, etc.
“
500 kV link to SCE’s 500 kV system”
NO NEED ESTABLISHED It was made clear in the LEAPS Final EIS prepared
by FERC that SCE does not need LEAPS power, therefore a 500 kV connection
to SCE service territory is unnecessary for the project. If LEAPS power
were to be used by SDG&E, it should be via a 230 kV line, since SDG&E
neither wants nor needs 500 kV power at the TE/VS point of junction.
“2007 Construction
Start”
UNLIKELY TNHC has not yet prepared the draft Environmental Impact Report
(EIR) which is likely to have substantial and substantive comments.
This prognosis is based on the fact that nearly every state and federal
agency that commented on the EIS documents found the final EIS to be
deficient, as evidenced by agency comments submitted under Docket P-11858.
Following the public comment period, the Final EIR must then be prepared,
and the State Water Board must use this document to ascertain whether
a Water Quality Certification should be granted. Only after this process
is completed can FERC consider whether or not to grant the license,
and this action will be followed by certain legal challenge. Because
we are now nearly half way through 2007, it is highly unlikely that
this project will begin construction in 2007.
“Critical asset
facilitating Statewide management of renewables”
FALSE There is an active and comprehensive plan in place to develop projects
that will enable load centers throughout Southern California to access
the renewable power sources in California and other states. NONE of
the studies that I have evaluated pursuant to these plans and developed
by programs such as CARTS, CSRTP, TCSG, STEP, etc. have relied on LEAPS-TE/VS
to ensure that SCE, SDG&E, PG&E, or LADWP are able to connect
to renewables.
“Promotes attainment
of RPS and GHG goals”
FALSE As indicated above, it appears that no electrical transmission
company or entity is relying on LEAPS to meet their RPS goals. In addition,
LEAPS does not provide electricity that can be used to meet their RPS
goals, since LEAPS does not qualify as a renewable asset according
to the CEC Renewables Portfolio Standard Eligibility Guidebook. Moreover,
LEAPS contributes substantially to the formation of Greenhouse Gases,
because it requires 20% more electricity during the pumping stage than
it releases during the generation stage, and no provisions have been
made to operate the pumps using energy from non-combustion sources.
If, on the other hand, it were proposed to operate LEAPS with a renewable
energy source (such as proposed by LADWP for their Castaic power plant),
then it could be legitimately claimed that LEAPS promotes attainment
of GHG goals. However, no such arrangements have been made.
“Complementary to SDG&E’s
Sunpath to create backbone”
MISLEADING AND INACCURATE CAISO clarifies that Sunrise will address
SDG&E
congestion/reliability problems, and Green Path will enable SDG&E
to meet RPS goals. Taken together as Sun Path, these projects address
SDG&E needs within CAISO’s planning horizon. LEAPS will not
create a backbone for SDG&E because SDG&E does not want or need
500 kV power on the Talega-Escondido line. Most importantly, CAISO and
the STEP have ascertained that LEAPS will not have project benefits which
offset it’s costs [page 1-5 of the Final EIS]. So why would CEC
consider a project in their corridor planning effort if it is too expensive
and provides no added benefits beyond those anticipated by other CAISO-approved
projects?
FROM PAGE 3 OF THE TNHC PRESENTATION:
“ TE/VS has a 1,600-MW design capacity”
MISLEADING From this statement, it appears that either FERC is improperly
permitting this project with a 1,000 MW capacity [page 1-6 of the Final
EIS] or TNHC intends to construct a larger and more substantial system
than what is anticipated by FERC.
“TE/VS Public
Lands Route”
MISLEADING Portions of the LEAPS project are on developed private lands,
and a substantial portion of the transmission line (approximately 30%)
are on or immediately adjacent to private property. I urge the CEC
to not be mislead on this point.
“TE/VS Only
500 kV link from San Diego to California Grid”
INACCURATE AND MISLEADING The Sunrise Powerlink provides a new 500 kV
line into San Diego that will be connected to the California grid via
the Green Path project at full build out. This combined “Sun
Path” project will provide an interconnection between the Serrano-Valley-Devers
line to the Imperial Valley station, which is linked to the Sunrise
Powerlink. As reported at the most recent STEP meeting (March, 2007),
LADWP is working on an interconnection with SCE for the northernmost
portion the Green Path Project. In other words, the Sun Path project
will also provide a 500 kV line into San Diego that is connected to
the California Grid. Of course, the Sun Path project will provide SDG&E
with 500 kV power when and where it is needed, unlike the LEAPS project,
which dumps 500 kV power at an SDG&E location that requires 230
kV power. In fact, the inconvenience of the LEAPS project will force
SDG&E to spend nearly $2 Billion to accommodate the LEAPS connection
at 500 kV [Chapter VII, page 26 of Supplemental Testimony from SDG&E
to the CPUC on January 26, 2007].
“TE/VS Links
available renewable resources (e.g. Tehachapi) for use in San Diego”
INACCURATE AND MISLEADING The second report of the Tehachapi Collaborative
Study Group (TCSG) places most of the burden on SCE (shared somewhat
by CAISO) to determine transmission infrastructure necessary to bring
Tehachapi power to SCE and SDG&E territories [Volume 2 of Second
TCSG Report, April 18, 2006]. SCE presented the Tehachapi Transmission
Project to the CPUC in December, 2006, and CAISO approved the project
on January 18, 2007. In these actions, neither SCE nor CAISO identify
LEAPS as a component in the Tehachapi Transmission project, nor do they
rely on LEAPS in any capacity to transmit Tehachapi power. Moreover,
the Sun Path project is expected to provide opportunities to SDG&E
to meet their RPS goals. Justification for this statement by TNHC is
lacking, since it is not at all clear how TE/VS will play any role in
transmitting renewable resources to San Diego.
“TE/VS Interconnect
System Impact Studies Complete”
FALSE Recent studies of the TE/VS component of the LEAPS project conducted
by CAISO considered the system impacts of TE/VS only in the presence
of both Tehachapi and Sun Path. These results clearly indicate that
TE/VS does not provide additional reliability benefits [see the May
1, 2007 CAISO response to FERC’s Order on Rate Request]. CAISO
has not performed a detailed impact study of the TE/VS component and,
judging from CAISO’s response to FERC, it is unlikely that one
will be conducted in the near future. Perhaps TNHC believes that the
study conducted by John Kyei [May 17, 2004 STEP meeting] constitutes
an adequate impact analysis of TE/VS, but a close inspection of this
study reveals that it did not consider the additional benefits of the
fully built Green Path project when linked with the Sunrise project
(i.e. Sun Path) in the comparison between TE/VS and Sunrise. Aside
from the fact that the Kyei study reveals TE/VS and Sunrise to have
roughly equivalent system impacts, the Kyei study is not particularly
relevant and should not be relied upon by CEC in determining the appropriateness
of including LEAPS-TE/VS in any In-State Transmission Corridor Plan.
Note: According to the May 2007 CAISO Generator Interconnection Queue,
it appears that the System Impact and Facilities Studies of the pumped
storage component of the LEAPS project are complete, but system impact
studies of the TE/VS component have not even begun. As transmission infrastructure,
TE/VS will undergo an entirely different procedure than the LGIP that
has been pursued for the pumped storage component. TNHC has applied to
CAISO for consideration as a Participating Transmission Owner [see February
2007 submittal] but this application has not been approved and no substantive
action by CAISO has been taken pursuant thereto. In fact, CAISO is not
likely to proceed on the TNHC PTO application until other matters with
FERC are resolved [per conversation with CAISO staff June 11, 2007]
“TE/VS Grid
connection graded by CAISO”
FALSE The extent of CAISO’s analysis of the TE/VS grid interconnection
is summarized in CAISO’s May 1, 2007 comments to FERC that the
LEAPS transmission line is not needed to solve any reliability problem.
While TNHC’s intent in making this statement is not clear, it is
certainly clear that substantial work must still be completed before
the TE/VS component of LEAPS is considered “graded” by CAISO
(whatever that means).
FROM PAGE 6 OF THE TNHC PRESENTATION:
“ TE/VS interconnect construction can commence in 2007”
NOT LIKELY See above comments.
“FERC has independently
evaluated need for the TE/VS interconnect”
FALSE A review of the “Purpose” and “Need” statements
found in the Final EIS reveals that FERC only relies on Kyei’s
and other STEP studies in their attempt to justify a need for the TE/VS
line [see Section 1.2 of the Final EIS]. Indeed, the Final EIS provides
no indication of any independent assessment conducted by FERC, even though
the Final EIS is precisely the document where such studies would be included.
Therefore, TNHC’s assertion that FERC had independently established
the need for at TE/VS interconnect does not appear to be supported by
any FERC published documents.
“TE/VS interconnect
has the support of affected federal agencies”
INACCURATE AND MISLEADING Numerous federal agencies (including the
EPA and the U.S. Department of Fish & Wildlife) have gone on record
that the analyses completed pursuant to this project are incomplete,
and indeed it appears that the Final EIS is deficient. In fact, until
a Clean Water Certification is obtained (and it is not guaranteed that
one will be granted by the State Water Board) FERC cannot even approve
the project because a hydro license cannot be issued without this certification.
Therefore it is not necessarily true that this project has the “support
of affected federal agencies”.
“ TE/VS interconnect allows for storage of renewable
resources”
FALSE This statement is false and shall remain false until such time
as TNHC makes arrangements to power the LEAPS water pumps with renewable
energy (as LADWP is doing with their Castaic power plant).
“TE/VS interconnect
improves System Reliability”
FALSE The TE/VS component of LEAPS is not even “needed to solve
any reliability problem” [CAISO’s May 1, 2007 response to
FERC]. So how then can TNHC assert that it will improve system reliability?
FROM PAGE 7 OF THE TNHC PRESENTATION:
“ TE/VS interconnect provides access to renewable energy
such as Tehachapi”
MISLEADING See above comments
“TE/VS interconnect
provides congestion mitigation”
FALSE This statement is not supported by the data, particularly in light
of the status of the Sunrise Powerlink project.
“TE/VS interconnect
has minimal environmental costs”
FALSE The environmental costs and impacts of the LEAPS project have NOT
YET BEEN ESTABLISHED as evidenced by all the deferred impact and mitigation
analyses contained in the Final EIS. The CEQA process has not even
begun, and the State Water Board has not received the data necessary
to ascertain the impact on state water resources. In fact, the State
Water Board and the EPA have commented repeatedly on the inadequacies
and incompleteness of the environmental assessment included in the
EIS [see FERC filings under Docket P-11858]. Finally, and perhaps most
disturbing of all, this project will create a new corridor in the pristine
and virtually untouched portions of the Cleveland National Forest.
For the record, the Cleveland National Forest is surrounded by Riverside,
Orange, San Diego, Los Angeles and San Bernardino Counties, and is
the only undeveloped area of substantial size in this region (which
is confirmed by a quick glance at any area satellite photo). The inclusion
of the LEAPS project in a state or federal Energy Corridor Plan will
also increase the environmental impacts exponentially, since it will
provide a vehicle for other transmission projects to be located in
the same area. The statement that this project has “minimal environmental
costs” is absurd on its face, and it is certainly not supported
by the facts.
FROM PAGE 9 OF THE TNHC PRESENTATION:
“
SDG&E/SCE/CAISO System impact studies and interconnection studies
completed”
INACCURATE AND MISLEADING As indicated in the May 1, 2007 response to
FERC, CAISO has only conducted an interim study that includes a preliminary
reliability analysis of the TE/VS portion of the LEAPS project. In addition,
CAISO has not processed the PTO application submitted by TNHC in February,
nor has CAISO approved the TE/VS project for grid connection. It is true
that CAISO has completed the system impact study of connecting the pumped
storage project to the grid, however this factor is not particularly
relevant to the CEC in determining whether or not to include the TE/VS
component in a draft corridor plan.
“CAISO interconnect
approval granted in March 2007”
INACCURATE AND MISLEADING CAISO has only considered interconnection of
the pumped storage component of the LEAPS project. CAISO has not processed
the TNHC PTO application, and has not approved the TE/VS interconnection
project. Since the TE/VS component will be the subject of any CEC corridor
debate, it is rather disingenuous to give CEC a false impression that
CAISO has approved the interconnection of TE/VS as a grid asset.
FROM PAGE 12 OF THE TNHC PRESENTATION
“ CAISO found 150+ million in annual benefits provided
by LEAPS”
FALSE CAISO published a preliminary benefits analysis of LEAPS [CSRTP
Interim Memorandum submitted to the Board of Governors in August of 2006]
which quantifies some economic benefits (albeit much less than $150 million)
but these results are skewed because they are derived from the assumption
that LEAPS sponsors would receive payment through the TAC. Of course,
this economic analysis is probably no longer relevant, because CAISO
has now elected to treat LEAPS as a generation asset rather than a transmission
asset. Moreover, the California Electricity Oversight Board believes
that LEAPS project will not provide ratepayers with any economic benefit
[CEOB Comments to FERC on May 1, 2007 -Docket ER06-278].
“LEAPS benefits
RPS and greenhouse gas emission reduction goals”
FALSE As clarified above, LEAPS has not been configured to operate with
renewable energy, therefore it will not provide RPS benefits. With
respect to greenhouse gas emission reduction goals, the project is
only 83.3% efficient, which means LEAPS will create 20% more greenhouse
gases per MW than combustion-based generators.
PAGES 13-18 DOES LEAPS MEETING CEC CORRIDOR ELIGIBILITY CRITERIA?
“ LEAPS is needed by 2017 to ensure reliability of power
imported to San Diego”
FALSE CAISO has found that LEAPS is not needed to solve any reliability
problem. In fact, the reliability problems that are caused by LEAPS will
be mitigated by the Sun Path Project [August 31, 2006 interim report
to the CAISO Board of Governors]. TNHC claims that FERC has independently
identified reliability benefits, but FERC failed to mention these benefits
in the Final EIS that was just released in January.
“LEAPS is needed
by 2017 to relieve congestion and connect San Diego to the Grid”
FALSE The only documents and studies asserting that LEAPS relieves
congestion are those which compare LEAPS to the Sunrise Project, and
all these documents
clarify that only one of these projects is necessary to address San Diego’s
congestion problems. Because the Sunrise project is much further along
in the entitlement process than LEAPS, it is unlikely that LEAPS will
provide any congestion relief to the California grid. Moreover, the CAISO
approved Sunrise and Green Path projects at full build out will connect
San Diego to the grid without LEAPS.
“LEAPS is needed
by 2017 to ensure access to renewables from the north”
FALSE Sunrise and the expanded Green Path will provide SDG&E with
access to renewables from the north and east without relying on LEAPS.
It is unlikely that LEAPS will play a role in distributing Tehachapi
power to SDG&E since SCE, LADWP and PG&E are expanding their
transmission infrastructure to address the issue of accessing renewables
without LEAPS.
“ LEAPS is near a load center and is threatened by continued development”
INNACURATE AND MISLEADING TNHC indicates that LEAPS will employs a “public
lands route” so why is the project threatened by continued development?
In fact the Final EIS trivializes the economic and environmental impacts
of LEAPS to privately held lands because the project is primarily on
federal lands. It is rather duplicitous to now claim that this particular
CEC Corridor criterion applies to the LEAPS project.
“LEAPS allows
storage for renewables, facilitates attainment of RPS goals and reduces
GHG”
FALSE These claims are effectively eliminated in the comments provided
above.
“Identified
by DOE as draft National Interest Electric Transmission Corridor”
FALSE TNHC appears to claim that LEAPS has been identified by the DOE
in their draft National Interest Electric Transmission Corridor, which
is not true. The DOE just released the latest draft of the Southwest
Area National Corridor, which designates a broad area that encompasses
a large number of electricity sources and sinks. It does not in any way
endorse a particular project and it certainly does not identify LEAPS
in the maps that have been prepared. This fact was confirmed in a conversation
last week with DOE staff in Washington DC who are working on the Section
1221 National Interest Energy Transmission Corridor Project.
“Identified
by USFS under Section 368”
FALSE As with the National Interest Electric Transmission Corridor comment,
it appears that TNHC claims that LEAPS is included in the draft Section
368 Energy Corridor Map, which is, of course, untrue. Per a June 12,
2007 conversation with Mr. Virgil Mink of the Trabuco Ranger District
(with jurisdiction over the Cleveland National Forest), LEAPS is not
(nor has it ever been) included in any 368 corridor maps prepared submitted
to the DOE by the USFS, including the most recent submittal. Section
368 corridors are up to a mile wide, limited to federal lands, and
established for many purposes including transportation of oil and natural
gas. I understand that CAISO and LEAPS proponents have requested that
the LEAPS project be designated as a Section 368 corridor, but these
requests do not appear to have been granted.
In this submittal, I have included specific citations and supplemental
information to substantiate the assertions made and to factually clarify
the actual status and circumstance of the LEAPS project. Should you
require additional information, please contact me at AirSpecial@aol.com.
Thank you for this opportunity to provide comment, and I appreciate
your time and attention to this matter.
Sincerely,
Jacqueline Ayer