Presented to the EVMWD Finance & Administrative
Committee Meeting on 5/15/07
by Doug Pinnow
During the past several years,
it has been very difficult for EVMWD’s
ratepayers to critically review the District’s involvement in the
LEAPS Project for two main reasons. First, most of the business issues
relating to this project have been discussed in Board meetings during
sessions that were closed to the public. And second, the District’s
anticipated expenditures on the LEAPS Project have not been included
in past annual budgets.
There is much to be said
about the practice of limiting the public’s
knowledge about LEAPS using closed sessions. However, today, I’d
like to limit my comments to the second of these two issues. That is,
properly budgeting for LEAPS going forward in fiscal year 2007-2008.
In the past, the District
justified not including expenditures for LEAPS in the annual Budget
by taking the position that these expenditures were
effectively “loans” from EVMWD to The Nevada Hydro Company
(Nevada Hydro) that would be repaid. In view of the likely repayment,
the expenditures were deemed to be exempt from inclusion in the Budget.
There is some logic that might
support this position in the past if there was a reasonable probability
that Nevada Hydro would, in fact,
repay the “loans” at some future date.
However, in view of significant developments that occurred during the
past year, it now appears that the probability of repayment by Nevada
Hydro is extremely small, near to zero. In view of this, it is important
that EVMWD modify past practices and include expenditures on LEAPS in
the FY 2007-2008 Budget. The following is a summary of the five most
important developments:
1. The only written document describing the Development Agreement between
EVMWD and Nevada Hydro for the LEAPS Project was signed and dated in
1997. During the past year, the public was told at several different
Board meetings that this Agreement was so out of date that it was no
longer considered relevant by EVMWD and that the negotiations to revise
this Agreement were near to being completed. Later, however, Mr. Ron
Young advised the Federal Energy Regulator Commission (FERC) by a letter
dated November 22, 2006 that the negotiations for a revised Agreement
had reached an impasse. It is my understanding that the impasse continues
to date.
Thus, there may be no current Agreement that requires Nevada Hydro to
repay anything.
2. The other possibility is that certain terms in the 1997 Agreement,
including the repayment clauses, may still be considered to be in effect.
The actual wording in the 1997 Agreement states that Nevada Hydro:
will reimburse District for all of its expenditures
but only under the condition that there is a
successful closing of all financing and/or equity contribution required
to construct and operate the [LEAPS] project.
Before going on, it should
be noted that the 1997 Agreement speaks only to EVMWD expenditures.
Nowhere does it categorize these expenditures
as “loans”. Nor, does the Agreement guarantee repayment
to EVMWD. In fact, the present situation is quite the opposite, in
view
of the developments described next.
3. The climate for private investment in hydroelectric projects such
as
LEAPS is very poor. In a letter dated October 2, 2006, the FERC
advised that during the past 20 years they have issued 45 preliminary
permits to enable developers to study the potential for building
pumped-storage projects similar to LEAPS. But none of the projects
has yet received financing.
4. In a report from the California Electricity Oversight Board (CEOB)
to FERC dated May 1, 2007 it was reported that:
During the April 19, 2007, public CAISO Board of Governors meeting,
Governor Tim Gage asked whether the LEAPS plant was viable strictly as
a merchant generator. TNHC [Nevada Hydro] responded that the LEAPS project
was not viable strictly as a merchant plant.
In view of this admission by Nevada Hydro, it is highly unlikely (nearly
inconceivable) that private investment will be made in the LEAPS Project.
5. The only alternative possibility for financing the LEAPS project
was to have it paid for by the public. A specific concept had been proposed
in November, 2005 by Nevada Hydro to add the cost for LEAPS to the Transmission
Access Charges (TAC) on monthly bills paid by the California electricity
ratepayers.
This possibility has been eliminated by a statement made by the California
Independent Systems Operator (CAISO) on May 1st that:
...the CAISO had concluded that recovery of the costs of the pumped
storage facility portion of the TNHC [Nevada Hydro] combined proposed
project [the LEAPS Project] through the CAIOS's transmission Access Charge
(AC) should not be allowed..,
CAISO went on to say:
Allowing TNHC [Nevada Hydro] to recover the costs of the facilities
that provide these services via guaranteed cost recovery in the TAC while
other providers of these services must face the risks of recovering their
costs in the market is unduly discriminatory and inconsistent with fundamental
market principles.
In summary, there is no way that the hydroelectric power plant can be
financed, either publicly or privately.
However, there may be one last hope that EVMWD may recover their cumulative
expenditures on LEAPS, which now exceed $3 million, from Nevada Hydro.
I decided to mention this hope here because it is, at best, a misplaced
hope.
The statements above, made by the CEOB and the CAISO relate to the hydroelectric
power plant associated with LEAPS. They do not relate to the other component
of the LEAPS Project that is a high voltage electrical transmission line
that is proposed to run through the Cleveland National Forest. It is
broadly believed that this transmission line might be economically viable
as a stand alone Project (without the hydroelectric power plant) and
Nevada Hydro seems keen on moving forward with its financing and construction.
However, EVMWD, as a co-applicant with Nevada Hydro for the LEAPS Project,
has consistently taken the position that they have no interest or desire
to participate in a power lines only project. This position is strongly
emphasized by Ron Young in his letter to FERC dated November 22, 2006.
There he states:
..the District will
not be a party to any effort to obtain …..
authority to construct a transmission-only project.
That leaves Nevada Hydro in
an awkward position because it would be very difficult for them to
go forward with the power lines project without
EVMWD’s support.
But, it’s been rumored
that Nevada Hydro may be willing to guarantee EVMWD full payment for
their expenditures on LEAPS if the District changes
their position to support the power lines only project.
While it may, at first, appear attractive for EVMWD to consider accepting
such an offer from Nevada Hydro in order to recover the $3 to $3.5 million
that has already been expended on LEAPS, this action would likely produce
a new and far more costly problem for EVMWD.
The new problem would be that
there is no sound justification for EVMWD to be involved in a power
lines only project. So, by helping Nevada Hydro
to realize the power lines, EVMWD would be exposing themselves to major
lawsuits from property owners along the path of the power lines who might
claim that EVMWD’s overreaching support of the power lines has
caused their property values to diminish.
Loss of property values is
a very serious and likely possibility. In fact, FERC mentioned in the
Environmental Impact Statement (EIS) that
they prepared for the LEAPS Project that values have fallen in the range
from 1% to 10% but are sometimes considerably greater for properties
near to similar power projects. FERC specifically mentions that the greatest
potential for negative effects on property values lies with … the
transmission line.
One can only begin to realize the magnitude of this potential liability
by noting that the combined property values in just two communities,
La Cresta and Tenaja, that will be passed by the power lines, if built,
exceed $2 billion. A loss of, say, 5% of that amount, which is in the
middle of the range suggested by FERC, would equal a liability in excess
of $100 million.
So, it seems it would be a very bad decision for EVMWD to accept $3
million, or so, from Nevada Hydro only to take on a liability in excess
of $100 million.
The bottom line is that going forward into the FY 2007-2008, EVMWD should
properly budget for all future LEAPS expenditures because there is no
longer any realistic probability that Nevada Hydro will reimburse the
District for these expenditures..
Further, the 2007-2008 Budget should include provisions for dealing
with the $3.5 million, or so, loss of the previously anticipated repayment
from Nevada Hydro.