LEAPS is the abbreviation for Lake Elsinore Advanced Pumped Storage
Project. The Project includes both a hydroelectric pump/storage power
plant and associated high voltage power transmission lines to connect
the power plant to the high voltage grid in California.
All pump/storage power plants require a large body of water, like Lake
Elsinore, and nearby mountains where a relatively large reservoir exists
or can be built. In the case of the LEAPS Project, the plan is to build
a new reservoir in the mountains west of Lake Elsinore. The reservoir
would have a surface area of approximately 100 acres and it would be
formed in a natural canyon by constructing a 180-foot high dam. The lake
and reservoir would be interconnected by one or two large pipes 12 to
20 feet in diameter.
There would be very large
rotating impellers in the pipes that would be electrically energized
by large motor/generators. When the cost of
electricity on the grid is low, typically during the night, the motor/generators
would operate as motors to rotate the impellers and pump approximately
10% of Lake Elsinore’s water up the mountain and into the reservoir.
Then, during hours of peak electricity demand (when the price of electricity
is high), the water in the reservoir would be flushed back down the pipes
into the lake causing the impellers to rotate and their associated motor/generators
would operate as generators to produce electricity that can be delivered
back to the grid.
The economic viability of such a power plant depends on two principal
factors (1) the differential cost of electricity during peak and low
demand periods and (2) the cost to construct the power plant.
The economic viability of
the LEAPS power plant by itself does not appear to be favorable. The
Federal Energy Regulatory Commission (FERC) has
estimated that if this power plant were built, it would cost the California
ratepayers an additional $120 million per year on their electricity bills
to operate it. (see The Nitty-Gritty
of the LEAPS’ Eonomics.)
A picture of the LEAPS Project (see What
is LEAPS?) has been prepared
by the opponents of the Project to highlight its principle problems and
risks.
Nevertheless, this picture is helpful to visualize the geographic scope
of the Project.
The most complete description
of the entire Project is found in a 500 + page Environmental Impact
Statement for Hydropower License: Lake Elsinore
Advanced Pumped Storage Project (FERC Project No. 11858) dated January
31, 2007. This document is available under references and
on the Federal Energy Regulatory Commission’s (FERC’s) web
site www.ferc.gov in
their “e-Library”.
There the Federal Government estimates the total Project construction
cost to be $1.3 billion.
This Project was conceived by the Elsinore Valley Municipal Water District
(EVMWD) in 1988 as a way to produce a modest amount of electrical power
during times of peak usage and, more importantly, to implement a strategy
to stabilize the water level in the lake. The concept for stabilization
was straightforward. Operation of a hydroelectric power plant would require
some minimum level of water in the lake and the owners of this plant
would have the incentive to pay the price necessary to maintain the level
in periods of drought.
The initial plans were for
only a 240 Megawatt power plant and a direct high voltage power line
running to the north to connect to the electrical
grid managed by Southern California Edison. The power line was to be
sized to match the power plant’s output.
Over the years, the planned
output of the power plant has been increased to the present rating
of 500 Megawatts (to achieve a more favorable economy
of scale) and the planned power lines have been extended both north and
south of the power plant running approximately 30 miles through the Cleveland
National Forest. The power lines are now sized to transmit 1,600 Megawatts
of power. Thus, in its present embodiment, the power lines would have
over three times the maximum output capacity rating of the power plant.
As such, the power lines have evolved from a simple connection
of the power plant to the grid into becoming a major power transmission
artery
between San Diego Gas & Electric in the south and Southern California
Edison in the north.
Opponents of the LEAPS Project say that if the power plant is not economically
viable it should not be built. That would leave just the power lines
though the Cleveland National Forest. And the opponents go on to say
that if the power plant is not built on the edge of the Forest, there
is no further justification for running power lines through the Cleveland
National Forest.
There are numerous alternate
paths for north-south running power lines that do not require encroachment
on the Forest. In fact, San Diego Gas & Electric
made a specific proposal for such a power line to the California Public
Utilities Commission (CPUC) in 2001 and again in 2003. However, their
proposal was denied by the CPUC for not being in the best interest of
the ratepayers.
Supporters of the LEAPS Project contend that the overall Project is
economically viable and it should be built. Opponents point out that
FERC has stated in a letter dated October 2, 2006 (see FERC
letter) that
no pump/storage hydroelectric projects have been built during the past
20 years in the United States even though 5 licenses were granted. The
reason that the licensed plants were not built was lack of sufficient
investor interest. This is the ultimate test of economic viability.
So long as LEAPS remains a
hydroelectric project, it can sidestep the CPUC licensing process and
be licensed directly by the Federal Government
(FERC). It is generally believed that the Federal Government is more
favorably inclined to grant licenses than the CPUC. However, concern
over the possible lack of economic viability of the pump/storage power
plant raises serious questions as to the appropriate venue for licensing
this Project. That’s because the only economically viable aspect
of the LEAPS Project appears to be the power lines.
THE RELATIONSHIP BETWEEN EVMWD AND NEVADA HYDRO
As mentioned above, the LEAPS Project was conceived by the EVMWD in
1988. By 1997, the EVMWD had completed preliminary studies and concluded
that it would be worthwhile to proceed. However, it was recognized
that the construction cost would be hundreds of millions of dollars.
At that time, EVMWD did not believe that it would be in the best interest
of their ratepayers to carry the burden of such an extraordinary expense.
So, EVMWD solicited proposals from private companies to take on all
of the financial and management responsibilities associated with the
project.
The only company that responded was a newly formed entity named The
Hydro Company. On May 15, 1997, EVMWD and The Hydro Company both signed
a Development Agreement for the LEAPS Project. This signing occurred
less than three months after The Hydro Company was incorporated in the
State of Nevada. Shortly thereafter, the Hydro Company filed to do business
in the California as The Nevada Hydro Company (see Who
is Nevada Hydro?)
One of the key objectives of the Development Agreement was included
in the Recitals:
WHEREAS, District (EVMWD) and Company (The Hydro Company) have agreed
it is mutually beneficial to enter into this Agreement to allow the Project
to proceed with minimal additional expenditure of public funds and without
delay in the FERC License application and in the construction and operation
of the Project.
The Agreement was signed by then President of the Board, Ben Wicke,
representing EVMWD, President H. L. Mitchell, representing The Hydro
Company and by John E. Brown, Legal Counsel for EVMWD. These names are
mentioned because all three individuals have subsequently influenced
the LEAPS Project in various ways, and each will be discussed in the
following.
First, ten years after, Ben
Wicke signed the Development Agreement, he is, once again President
of the EVMWD’s Board. He was re-elected
in 2006 after accepting substantial campaign contributions from Nevada
Hydro, as reported in the press (Valley
News and The Californian).
He told the press that he had no idea that the campaign money he accepted
had come from Nevada Hydro after
being “laundered” by a political action committee. Wicke
remains a strong advocate of the LEAPS Project and a loyal supporter
of Nevada Hydro.
This Development Agreement, which has no termination date, has remained
in effect up to the present. During 2006, the EVMWD Board of Directors
informed the public that the old Agreement was so out of date that there
was concern about its continued applicability and that a new Agreement
with Nevada Hydro was being negotiated. However, on November 22, 2006,
Ron Young, the General Manager of EVMWD notified FERC in a letter that
the negotiations with Nevada Hydro had reached an impasse. Thus, the
original Development Agreement continues to stand, but on shaky footing.
In broad terms, this Agreement
assigns to The Hydro Company the responsibilities of acquiring the
FERC license, securing investors to construct the Project
and to operate it after it is completed. Both EVMWD and Nevada Hydro
are the co-applicants for the FERC license. However, it is clear that
Nevada Hydro is an active participant in the Project to make a financial
gain while EVMWD’s interest is to stabilize the level of Lake Elsinore.
In 1999, the Development Agreement came close to falling apart as the
principals in Nevada Hydro were engaged in cross lawsuits. The episode
was reported in an article titled Criminal
probe faces hydro plant planner in the March 6, 1999 issue of The Press-Enterprise, a local newspaper.
The criminal probe led to the departure of H. L. Mitchell from The Hydro
Company. Recall, that he was the one who signed the 1997 Agreement.
Shortly after the criminal
probe was resolved, Nevada Hydro brought Enron Corporation in as their
partner in the LEAPS Project. This arrangement
was approved by EVMWD. However, by 2001, Enron’s legal problems
were mounting and they withdrew from the Project.
Many, who opposed the LEAPS
Project thought that it was “dead” after
ENRON had withdrawn. But, Nevada Hydro and EVMWD continued to quietly
move forward in a most unusual and suspect fashion that some say may
have been both unethical and illegal.
All the subsequent meetings between EVMWD and Nevada Hydro were conducted
as ad hoc meetings with no more than two of the five EVMWD Directors
in attendance. This allowed the Project to proceed without public scrutiny.
The results of the ad hoc meetings were shared with the other Directors
who supported the LEAPS Project. But then Director Chris Hyland, who
opposed the Project, and the public were left in the dark.
This shady practice continued
until the new EVMWD Board of Directors was installed early in 2007.
At that time, the Ad Hoc LEAPS Committee
was disbanded. However, to date, the public has been kept away from finding
out any significant details about the LEAPS Project or the strained relationship
between EVMWD and Nevada Hydro because all Board meetings that concern
LEAPS have been held in “closed sessions”. The stated justification
for this is the possibility of a potential lawsuit between EVMWD and
Nevada Hydro.
Many of the opponents of the
LEAPS Project have protested to the EVMWD Board about the ad hoc meetings
subverting the intent of the Brown Act,
which requires public access. While they recognized that it may have
been useful and acceptable to have ad hoc meetings for a limited duration
to resolve a specific problem, they feel that stringing out such meetings
for five years was excessive and an abuse of the Board’s authority.
The current attorney for EVMWD, John Brown (who also signed the 1997
Agreement), has countered that the Brown Act sets no specific limits
on the
duration of ad hoc meetings. His actions suggest that he is more inclined
to protect the interests of the Board members than the public intersts.
Regardless of which side of
this argument is correct, it’s clear
that the secret ad hoc meetings and now the “closed sessions” have
effectively eliminated public oversight.
Behind the veil of secrecy, EVMWD started to loan Nevada Hydro substantial
amounts of money for undisclosed purposes. During the period between
the beginning of 2001 and June 30, 2006, the unpaid balance of loans
from EVMWD to Nevada Hydro was $1,354,905.96, as documented. The loans
invoiced during just the first half of 2006 totaled $427,815.36. It is
believed that the loans have continued to the present and that total
amount now exceeds $3 million. Further, there can be no assurance that
the loans will ever be repaid because the 1997 Agreement with Nevada
Hydro only requires repayment if the LEAPS Project is actually financed
and built.
Making such loans by EVMWD seems to subvert the intent of the Development
Agreement. Recall that it was entered into by EVMWD to proceed with
minimal additional expenditure of public funds. Yet, in recent years
over $3 million of public funds has been put at risk by EVMWD. This
includes substantial funds spent in the fall and winter of 2006-2007
to pay for a television ad series that promoted the LEAPS Project to
the general public.
An example of this questionable loan practice is a typical
loan invoice made by EVMWD and dated June 15, 2006. It contains no information for
how the $137,197.91invoiced amount was used. Thus, the public has been
denied the ability to meaningfully review the financial aspects of the
LEAPS Project. Further, EVMWD has continued to be unresponsive to repeated
requests made by the public and by ex-Director Chris Hyland (who opposes
the LEAPS Project) for more detailed information to support the loans
made to Nevada Hydro.
There is a serious concern
that public money loaned by EVMWD to Nevada Hydro may have been included
in the money laundered by Nevada Hydro to
support the election of Directors who are favorably inclined to support
the LEAPS Project and Nevada Hydro. “Buying” Directors in
this way would be a serious violation of California laws. But, at present
there is no proof that this has been done. However, suspicion remains
high, in view of the fact that Nevada Hydro does not seem to have any
other business interests besides LEAPS that could bring in revenues to
support the campaign contributions.
RECENT DEVELOPMENTS
On April 16, 2007 the Board of Governors of the California Independent
Systems Operator (CAISO) held a meeting open to the public about the
LEAPS Project. One of the Governors asked a representative of Nevada
Hydro if the LEAPS hydroelectric power plant would be economically viable
as a merchant generator. Nevada Hydro gave a negative response to that
question.
This is the first time that
Nevada Hydro has admitted that the LEAPS power plant would not be economically
viable. But viability was not necessary
because Nevada Hydro had been pressing for a favorable ruling from the
CAISO that the cost for LEAPS should be added to the Transmission Access
Charges that are paid by all California electrical ratepayers on their
monthly bills. At that meeting, the CAISO’s Board of Governors
denied Nevada Hydro’s request, saying that
Allowing TNHC [Nevada Hydro] to recover the costs of the facilities
that provide these services via a guaranteed recovery in the TAC [Transmission
Access Charges] while other providers of these services must face the
risks of recovering their costs in the market is unduly discriminatory
and inconsistent with fundamental market principles.
This position and the admission by Nevada Hydro that the hydroelectric
power plant is not economically viable has sealed the fate of the LEAPS
hydroelectric power plant unless some future Government rescue attempt
is made.
However, the power lines initially
associated with the overall LEAPS Project have taken on a life of their
own. Nevada Hydro is keen on building
them while EVMWD’s public position is that they are not supportive
of the power lines without the hydroelectric power plant. It’s
generally believed that this difference is part of the reason for the
current impasse between EVMWD and Nevada Hydro in revising the old Development
Agreement.
The final chapter for LEAPS
is likely to focus on the whether the power lines should be built.
There are strong forces on both sides of this
issue that are gearing up for action. The opponents cite the extreme
fire hazard that aerial power lines would create not only in the Cleveland
National Forest but also in nearby communities, the loss of nearby property
values and concerns for negative health effects caused by the electromagnetic
radiation emitted from the power lines. On the other hand, the proponents
are driven not only by economic gains but also by their stated desire
to make the electrical power grid more robust to potential black-outs
caused by equipment failures or even by terrorists’ activities.
Since alternate pathways exist
for the power lines, like the one mentioned above that was proposed
by San Diego Gas & Electric in 2001 and 2003,
the decision for exactly where to build an interconnect power line between
SDG&E in the south and Southern California Edison (SCE) in the north
depends on a complex balance of raw political power, substantial amounts
of money, and risk to human life.
To make matters even more
complex, serious questions have been raised as to the need for any
such interconnect in view of other major power
projects started after LEAPS that will supply both SDG&E and SCE
with substantial amounts of power from the east. These include the Sunrise
Power Project supported by SDG&E and a major
multi-state effort to import power from coal fired power plants located in states east of California
that have plentiful coal deposits.