Page 1
DM1734747
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE
STATE OF CALIFORNIA
In the Matter of the Application of the Nevada
Hydro Company for a Certificate of Public
Convenience and Necessity for the Talega-
Escondido/Valley-Serrano 500-kV Interconnect
A.10-07-001
PROTEST OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E)
CONCERNING THE PROPONENT’S ENVIRONMENTAL ASSESSMENT
SUBMITTED BY THE NEVADA HYDRO COMPANY, INC.
JENNIFER R. HASBROUCK
ROBERT J. KANG
LAURA B. RENGER
Attorneys for
SOUTHERN CALIFORNIA EDISON COMPANY
2244 Walnut Grove Avenue
Post Office Box 800
Rosemead, California 91770
Telephone: (626) 302-6012
Facsimile:
(626) 302-2610
E-mail:
robert.kang@sce.com
Dated: July 6, 2010

Page 2
- 1 -
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE
STATE OF CALIFORNIA
In the Matter of the Application of the Nevada
Hydro Company for a Certificate of Public
Convenience and Necessity for the Talega-
Escondido/Valley-Serrano 500-kV Interconnect.
A.10-07-001
PROTEST OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E)
CONCERNING PROPONENT’S ENVIRONMENTAL ASSESSMENT SUBMITTED BY
THE NEVADA HYDRO COMPANY, INC.
I.
INTRODUCTION
Southern California Edison Company (“SCE”) respectfully submits its protest to The
Nevada Hydro Company, Inc.’s Proponent’s Environmental Assessment, filed on July 6, 2010
(“TNHC,” “2010 PEA,” respectively).
1
Similar to previous TNHC PEAs found deficient by the
Commission,
2
TNHC seeks a certificate of public convenience and necessity for a high-voltage
transmission line extending from SCE’s existing 500 kV transmission system in western
Riverside County to San Diego Gas & Electric Company’s (“SDG&E”) existing 230 kV
transmission system in northern San Diego County, the Talega-Escondido/Valley-Serrano 500
kV Interconnect (“TE/VS Project” or “Project”). TNHC also seeks Commission permission to
construct 115 kV elements to purportedly serve that region. Like TNHC’s previously submitted
1
SCE’s protest relates to the following: Application for a Certificate of Public Convenience and Necessity;
Proponent’s Environmental Assessment, In the Matter of the Application of The Nevada Hydro Company for a
Certificate of Public Convenience and Necessity for the Talega-Escondito/Valley Serrano 500-kV Interconnect
Project, No. A.10-07-001 (filed July 6, 2010)(“hereinafter “Application” and “2010 PEA,” respectively).
2
See Decision Dismissing Application Without Prejudice, Decision No. 09-04-006, Proceeding No. 09-02-012 &
No. 07-10-005, In the Matter of the Application of the Nevada Hydro Company for a Certificate of Public
Convenience and Necessity for the Talega-Escondido/Valley-Serrano 500-kV Interconnect, Public Utilities
Commission of California (issued April 17, 2009) (hereinafter “Order Dismissing Application” or “Order”), at
passim (discussing TNHC’s prior filing history).

Page 3
- 2 -
PEAs, the instant PEA remains critically incomplete, and it continues to include project elements
that are not needed to accomplish TNHC’s stated goals. SCE, thus, respectfully urges the
Commission to deem TNHC’s PEA incomplete and/or overbroad, as follows:
ƒ TNHC did not cure specific deficiencies identified by the Commission in the
Commission’s April 16, 2009 Order dismissing TNHC’s previous application and
PEA. In that Order, the Commission instructed TNHC to cure specific deficiencies
should TNHC file a new application.
3
For example, the Commission ordered
TNHC to include written confirmation from the United States Marine Corps
confirming that Marine Corps property would be made available to TNHC.
4
However, the 2010 PEA does not contain any such communication. Similarly, the
Commission instructed TNHC to provide certain details about its proposed 115 kV
project elements in order to allow for a meaningful review.
5
TNHC’s PEA is still
missing crucial detail.
ƒ TNHC did not adequately address environmental concerns relating to TE/VS
previously identified by SCE to the Commission. For example, SCE previously
informed the Commission that TNHC’s proposed Lake substation rests on a buried
fault, and that it lies adjacent to a FEMA-designated 500-year flood zone. TNHC did
not adequately respond to SCE’s concerns about the risks posed by siting a load-
serving substation at that location.
ƒ TNHC did not adequately study the potential impacts and risks posed by its 115 kV
and 500 kV project elements to SCE, California ISO or WECC systems. For
example, since TNHC did not initially include the 115 kV elements of its project in
its interconnection application to SCE, there have been no studies performed by SCE
3
Order Dismissing Application, supra note 2, at 9.
4
Order Dismissing Application, supra note 2, at 9 (instructing TNHC to cure deficiencies listed in Staff’s March
12, 2009 Deficiency Letter); see also Deficiency Letter from CPUC Staff to TNHC, dated March 12, 2009
(attached as Attachment 5 to Order Dismissing Application)(hereinafter “Staff Letter”), at 2.
5
Staff Letter, supra note 4, at 4-5; Order Dismissing Application, supra note 2, at 9.

Page 4
- 3 -
to determine the impact those 115 kV elements would have on SCE’s systems.
Notably, TNHC’s Federal Final Environmental Impact Study (“FEIS”), which
features prominently in TNHC’s CPCN application materials, also does not analyze
TNHC’s 115 kV project elements. Similarly, neither SCE, the California ISO nor
WECC, have conducted studies determining the impact that a stand-alone 500 kV
transmission line in this region would have on their respective systems. There are
also no studies confirming that such a line is, in fact, needed or cost effective.
ƒ Commission approval for the TE/VS Project should be made contingent on the
development of TNHC’s “LEAPS” Project – a proposed hydro pumped storage
facility that TNHC is concurrently pursuing at the Federal level. If the LEAPS
project is denied at the Federal level, then many aspects of TE/VS become
unnecessary. Therefore, SCE does not believe the Commission should review the
TE/VS project on a “stand-alone” basis as requested by TNHC.
ƒ Interconnection to both SCE’s and SDG&E’s systems is unnecessary to satisfy
TNHC’s stated goal of interconnecting LEAPS to the CAISO-controlled grid.
II.
TNHC HAS NOT CURED THE DEFICIENCIES PREVIOUSLY IDENTIFIED BY THE
COMMISSION IN THE COMMISSION’S APRIL 16, 2009 ORDER
TNHC’s PEA remain incomplete because TNHC did not cure specific deficiencies
previously identified by the Commission.
6
In its April 16, 2009 Order, the Commission
instructed TNHC to cure several deficiencies, including those referenced in a deficiency letter,
dated March 12, 2009, from Commission Staff to TNHC.
7
In that letter, Staff identified two
major problems with Nevada Hydro’s PEA: (1) the PEA did not contain written confirmation
6
Order Dismissing Application, supra note 2, at 5; Staff Letter, supra note 4, at passim.
7
Order Dismissing Application, supra note 2, at 9 (referring to Staff Letter, supra note 4).

Page 5
- 4 -
from the United States Marine Corps that the Marine Corps would make available a specific site
for a proposed TNHC substation; and (2) the PEA’s proposed 115 kV project elements did not
contain sufficient detail about those elements for the Commission to engage in meaningful
review.
8
These deficiencies remain uncorrected in TNHC’s current PEA. For example, TNHC’s
application states that interconnection with SDG&E will take place at a “new substation in the
vicinity of United States Marine Corps Camp Joseph H. Pendleton,” thereby confirming that
TNHC still seeks to include a substation on Marine Corps property.
9
However, TNHC did not
provide written proof that the Marine Corps identified a substation site, or that such a site would
be made available to TNHC.
10
Since TNHC’s 2010 PEA lacks written confirmation from the
Marine Corps about the use of its property, Staff’s first concern remains unresolved.
Staff’s second concern remains equally unresolved. In its deficiency letter to TNHC,
Staff revealed the following problems about TNHC’s last PEA:
There is no information provided about where these [115 kV] project
elements and activities would be located. There is no information provided
in the PEA about where proposed and existing lines would share the rights-
of-way and poles, where lines would be underground, where street closures
would be required for construction, and where new poles would be required
and of what type, spacing and height. The text does not explain how 115 kV
transmission lines would be accommodated on existing local distribution
poles.
11
TNHC’s current PEA is still missing critical information required by Staff and the
Commission to conduct a meaningful review. For example, the PEA contains minimal
information about rights-of-ways. And as demonstrated by a vague reference to 115 kV line
extensions from the Lake site, the PEA does not provide meaningful detail about the 115 kV
lines coming from the Lake site.
12
Instead, to the extent TNHC provides information, it is both
8
Staff Letter, supra note 4, at passim.
9
Application, at 4.
10
2010 PEA, at 3-77 (Section 3.1.1.4) and 3-79 (table 3.1.1-1)(noting that TNHC may require approval from the
United States Marine Corps for use of Marine Corps real property).
11
Staff Letter, supra note 4, at 5.
12
2010 PEA, at 3.95.

Page 6
- 5 -
inconsistent and unclear. For example, on page 3.95 of the PEA, TNHC lists “attendant 500/115
kV transformers and 115 kV line extensions” as part of its Lake site. However, this equipment is
not listed in the more detailed description of the Lake site beginning on page 3.111. Thus, it is
unclear how those 115kV components will be used.
TNHC’s failure to resolve the concerns raised in Staff’s 2009 deficiency letter, combined
with TNHC’s use of inconsistent and unclear information, prevents the Commission from
meaningfully reviewing TNHC’s application and PEA. For these reasons, TNHC’s PEA should
be deemed incomplete by the Commission.
III.
TNHC’S PROPOSED “LAKE” SITE CONTINUES TO RAISE SERIOUS
ENVIRONMENTAL CONCERNS
TNHC’s PEA is also incomplete because it fails to adequately address environmental
deficiencies previously identified by SCE relating to the proposed location of its Lake substation.
These deficiencies arise out of the “combined” nature of TNHC’s proposed Lake
substation. TNHC is pursuing two actions in parallel: it is seeking Federal permission to develop
a hydroelectric pump storage facility titled “LEAPS” (Lake Elsinore Advanced Pump Storage
facility), and Commission permission to construct the allegedly “stand alone” TE/VS
transmission line.
13
TNHC first sought to interconnect its proposed LEAPS hydro facility to
SCE’s systems, and proposed siting a 500 kV switchyard at TNHC’s preferred Lake site. SCE
later informed TNHC that SCE would be developing a new 500/115 kV substation on an
approximately 50-acre site in the Glen Ivy/Alberhill area of unincorporated Riverside County
(the Alberhill site).
14
This substation is needed to address SCE’s load-serving needs, and thus
has independent utility from TNHC’s interconnection needs. TNHC responded by seeking
13
2010 PEA, at 1-1 (explaining TNHC’s filing posture).
14
SCE has since filed for a CPCN to construct this substation. See Amendment to the Application of Southern
California Edison Company (U 338-E) for a Certificate of Public Convenience and Necessity; Alberhill System
Project, No. 09-09-022 (original application filed Sept. 30, 2009; amended application filed March 15, 2010).

Page 7
- 6 -
Commission permission to build a combined facility purportedly capable of serving both
TNHC’s interconnection needs, and SCE’s load-serving needs, at the Lake site. However, as
SCE has previously indicated in response to past TNHC filings, TNHC’s proposal does not
adequately address a large number of environmental concerns.
15
For example, TNHC’s 2010
PEA:
ƒ Does not adequately address the concealed or buried fault lying directly beneath the
proposed Lake site, or how TNHC will adequately mitigate the risks posed by that
fault to a load-serving substation. The western-most portion of TNHC’s proposed
site is also crossed by a Late Quaternary age fault, but the PEA still does not
adequately evaluate fault rupture hazards at the Lake site.
ƒ Does not adequately address flood hazards, such as the fact that the proposed site is
adjacent to a FEMA-designated 500-year flood hazard zone, or the fact that the site is
immediately adjacent to a substantial active drainage channel which poses potential
flooding and erosion hazards.
TNHC has not adequately addressed the above environmental concerns. Until TNHC
does so, TNHC’s PEA should be deemed deficient by the Commission.
IV.
CRUCIAL ELEMENTS OF TNHC’S PROJECT HAVE NOT BEEN STUDIED; HAVE
NOT BEEN SHOWN TO BE NEEDED; AND HAVE NOT BEEN SHOWN TO BE COST-
EFFECTIVE
TNHC’s PEA is also incomplete because crucial elements relating to both the 115 kV and
500 kV elements of its Project remain unstudied. Without these studies, none of the interested
parties, nor the Commission, are capable of determining the impacts that TNHC’s project poses
15
Protest of Southern California Edison Company (U 338-E) Concerning the Revised Proponent’s Environmental
Assessment Submitted By the Nevada Hydro Company, In the Matter of the Application of the Nevada Hydro
Company for a Certificate of Public Convenience and Necessity for the Talega-Escondido/Valley-Serrano 500-
kV Interconnect, Proceeding No. A07-10-005 (filed Dec. 15, 2008), at passim.

Page 8
- 7 -
to SCE, California ISO or WECC systems. For example, since TNHC did not include 115 kV
elements in its initial LGIA application, SCE did not initiate any studies to determine the impact
those elements would have on SCE’s systems. However, load flow, short-circuit duty, and
contingency condition analyses must be performed before any definitive statements can be made
about such impact, and before TNHC’s PEA can be deemed complete. The PEA also does not
contain enough detail to determine the potential impacts should TNHC’s proposed 115 kV lines
between Santa Rosa Substation and the Elsinore and Skylark Substations be constructed and put
on-line; to determine whether the routes for those lines are feasible; or to determine whether
TNHC adequately evaluated alternative routes for its 115 kV project elements. Notably,
TNHC’s own FEIS, which TNHC relies upon in its request to obtain a CPCN, does not analyze
TNHC’s 115 kV project elements.
16
SCE is particularly concerned about the lack of these
studies, since TNHC’s project, if allowed to proceed, will affect SCE’s systems in ways
currently unknown to SCE.
TNHC’s 500 kV project elements remain similarly unstudied. For example, although the
2010 PEA describes the TE/VS Project as “part of the transmission grid,” the TE/VS Project has
only been studied as a gen-tie and the CAISO has not reviewed or approved of the Project as a
network addition.
17
WECC also did not perform a path rating study on the TE/VS Project.
Finally, TNHC itself did not include a study, pursuant to Public Utilities Code Section 1002.3,
demonstrating that the proposed line is cost effective.
In summary, the 115 kV project elements were not part of TNHC’s interconnection
request, and thus were not studied by SCE. Nor are they part of TNHC’s FERC FEIS.
Important aspects of TNHC’s 500 kV elements remain similarly unstudied. TNHC’s project will
affect SCE’s systems in as-yet unknown ways. There is also no indication that TNHC’s various
16
E.g., Application, at 9 (relying on FEIS); Final Environmental Impact Statement for Hydropower License, Lake
Elsinore Advanced Pumped Storage Project FERC Project No. 11858 (Docket No. P-11858) (issued for public
comment on Jan. 30, 2007), at passim.
17
Application, at 2.

Page 9
- 8 -
elements are needed, or that they are cost-effective. For these reasons, TNHC’s PEA should be
deemed incomplete by the Commission.
V.
THE PROJECT SHOULD BE COORDINATED WITH, AND MADE
CONTINGENT UPON, TNHC’S LEAPS PROJECT
As stated earlier, TNHC is concurrently pursuing FERC permission to develop its
LEAPS hydro pump facility and Commission permission to construct the “stand alone” TE/VS
transmission line.
18
However, these two projects are intertwined: one of the primary purposes
stated by TNHC of TE/VS is to interconnect LEAPS to the transmission systems of SCE and
SDG&E and the CAISO grid.
19
Accordingly, the Commission should not approve the TE/VS Project in isolation, or as a
stand alone project, separate from the LEAPS hydro facility, since the TE/VS Project is
dependent on LEAPS. If TNHC is unable to obtain Federal permission to construct LEAPS,
then many, if not all, aspects of the TE/VS project will not be needed to further those stated
goals. If the CPUC grants a CPCN for the TE/VS Project, it should be made contingent on the
construction of the LEAPS hydropower generation plant in order to satisfy the PEA-stated
primary purpose project goals. Construction should be consistent with the operating date of the
hydro facility.
20
18
E.g., 2010 PEA, at 1-1 (stating that TNHC’s project consists of two parts, and that TNHC only seeks CPUC
permission to construct the transmission portion), 3-74 (describing TE/VS as a “stand-alone” action).
19
E.g., 2010 PEA, at 2-5.
20
If the TE/VS Project were, in fact, a stand-alone transmission project, then it should have been reviewed under
the CAISO’s transmission planning process.

Page 10
- 9 -
VI.
THE PURPOSE AND NEED FOR INTERCONNECTION TO THE CAISO-
CONTROLLED GRID CAN BE MET WITH THE CONSTRUCTION OF ONE PART
OF THE PROJECT – THE CONNECTION TO EITHER SCE’S SYSTEM OR SDG&E’S
SYSTEM
One of the objectives of TNHC’s TE/VS Project, as stated in its PEA, is to take
advantage of water/geography features in the region, and by interconnecting LEAPS to the
CAISO grid to meet power needs in both San Diego and Los Angeles.
21
However, this objective
can be satisfied with the construction of one radial interconnection: connecting to either SCE’s
network or SDG&E’s network will provide the plant with access to the CAISO grid. By
contrast, constructing two radial interconnections that would connect the Project to both
networks are unnecessary, as a single radial interconnection to one system would be adequate for
a generation project the size of LEAPS. Once the LEAPS Project is interconnected to the
CAISO grid through either SCE’s or SDG&E’s system, the stored power will be capable of
being used in both regions. Two interconnections are not necessary to achieve this goal.
VII.
CONCLUSION
TNHC’s PEA should be deemed incomplete or overbroad on multiple grounds. First and
foremost, the PEA is incomplete because TNHC did not cure the specific deficiencies identified
by the Commission in its April 16, 2009 Order. TNHC has also not adequately addressed
preexisting concerns raised by SCE. TNHC’s PEA is also incomplete because TNHC did not
adequately study the potential impacts posed by its Project to SCE, California ISO and WECC
systems.
21
2010 PEA, at 2-4.

Page 11
- 10 -
Additionally, TNHC’s request to treat TE/VS as a stand-alone project is overbroad: the
Project, or some portion of it, is only needed if TNHC’s LEAPS Project is constructed. Thus the
CPCN should be contingent on the construction of LEAPS in order to satisfy the PEA-stated
primary project goals. Also, two generation tie lines are unnecessary to satisfy TNHC’s
interconnection goals. A single radial interconnection to either SCE or SDG&E is sufficient.
SCE reserves the right to raise further objections if additional details about the Project
and its intended use are provided. SCE intends to participate fully in the hearings on the TE/VS
Project.
Respectfully submitted,
JENNIFER R. HASBROUCK
ROBERT J. KANG
LAURA B. RENGER
/s/ Robert J. Kang
By: Robert J. Kang
Attorneys for
SOUTHERN CALIFORNIA EDISON COMPANY
2244 Walnut Grove Avenue
Post Office Box 800
Rosemead, California 91770
Telephone: (626) 302-6012
Facsimile:
(626) 302-2610
E-mail:
robert.kang@sce.com
Dated: July 6, 2010

Page 12
CERTIFICATE OF SERVICE
I hereby certify that, pursuant to the Commission’s Rules of Practice and Procedure,
I have this day served a true copy of the PROTEST OF SOUTHERN CALIFORNIA
EDISON COMPANY (U 338-E) CONCERNING THE PROPONENT’S
ENVIRONMENTAL ASSESSMENT SUBMITTED BY THE NEVADA HYDRO
COMPANY, INC., on all parties identified on the attached service list(s). Service was effected
by one or more means indicated below:
Transmitting the copies via e-mail to all parties who have provided an e-mail
address. First class mail will be used if electronic service cannot be effectuated.
Executed this 6th Day of July, 2010, at Rosemead, California.
__________________/s/ Alejandra Arzola________
Alejandra Arzola, Case Analyst
SOUTHERN CALIFORNIA EDISON COMPANY
2244 Walnut Grove Avenue
Post Office Box 800
Rosemead, California 91770

Page 13
PROCEEDING: A0902012 - THE NEVADA HYDRO CO.
FILER: THE NEVADA HYDRO COMPANY
LIST NAME: LIST
LAST CHANGED: JUNE 14, 2010
DOWNLOAD THE COMMA-DELIMITED FILE
ABOUT COMMA-DELIMITED FILES
Back to Service Lists Index
ARNOLD B. PODGORSKY MICHAEL J. THOMPSON
WRIGHT & TALISMAN, P.C. ATTORNEY AT LAW
1200 G STREET, N.W., SUITE 600 WRIGHT & TALISMAN, P.C.
WASHINGTON, DC 20005 1200 G STREET, N.W., SUITE 600
FOR: THE NEVADA HYDRO COMPANY WASHINGTON, DC 20005
FOR: THE NEVADA HYDRO COMPANY
JOHN BUSE JENNIFER HASBROUCK
CENTER FOR BIOLOGICAL DIVERSITY SOUTHERN CALIFORNIA EDISON COMPANY
5656 S. DORCHESTER AVE. NO 3 PO BOX 800
CHICAGO, IL 60637 2244 WALNUT GROVE AVENUE, PO BOX 800
FOR: CENTER FOR BIOLOGICAL DIVERSITY ROSEMEAD, CA 91770
FOR: SOUTHERN CALIFORNIA EDISON COMPANY
JENNIFER R. HASBROUCK LAURA B. RENGER
ATTORNEY AT LAW SOUTHERN CALIFORNIA EDISON COMPANY
SOUTHERN CALIFORNIA EDISON 2244 WALNUT GROVE AVENUE
PO BOX 800 ROSEMEAD, CA 91770
ROSEMEAD, CA 91770 FOR: SOUTHERN CALIFORNIA EDISON COMPANY
FOR: SOUTHERN CALIFORNIA EDISON
REXFORD WAIT PAUL A. SZYMANSKI
THE NEVADA HYDRO COMPANY ATTORNEY AT LAW
2416 CADES WAY SAN DIEGO GAS & ELECTRIC COMPANY
VISTA, CA 92081 101 ASH STREET HQ 12
FOR: THE NEVADA HYDRO COMPANY SAN DIEGO, CA 92101
FOR: SAN DIEGO GAS & ELECTRIC CO.
AUTUMN DEWOODY GENE FRICK
PROGRAMS DIRECTOR 4271 BAGGETT DR
INLAND EMPIRE WATERKEEPER RIVERSIDE, CA 92505
CPUC Home
CALIFORNIA PUBLIC UTILITIES COMMISSION
Service Lists
Parties
Page 1 of 5
CPUC - Service Lists - A0902012
7/6/2010
http://docs.cpuc.ca.gov/published/service_lists/A0902012_78210.htm

Page 14
3741 MERCED DRIVE, UNIT F2 FOR: SANTA ANA MOUNTAINS TASK FORCE OF
RIVERSIDE, CA 92503 THE SIERRA CLUB, AND FRIENDS OF THE
FOR: INLAND EMPIRE WATERKEEPER FOREST (TRABUCO DISTRICT) AND THE SANTA
ROSA PLATEAU
JOHN PECORA RUTH ATKINS
16336 GRAND AVENUE PRESIDENT
LAKE ELSINORE, CA 92530 LAKE ELSINORE HISTORICAL SOCIETY
FOR: JOHN PECORA
15237 LAKE TRAIL CIRCLE
LAKE ELSINORE, CA 92530
FOR: LAKE ELSINORE HISTORICAL SOCIETY
RONALD E YOUNG, P.E., DEE DOUGLAS PINNOW
GENERAL MANAGER 7 VIA DEL LAGO
ELSINORE VALLEY MUNICIPAL WATER DISTRICT LAKE ELSINORE, CA 92532
31315 CHANEY STREET FOR: DOUGLAS PINNOW
LAKE ELSINORE, CA 92531-3000
FOR: ELSINORE VALLEY MUNICIPAL WATER
DISTRICT
GREGORY HEIDEN STEPHEN E. VELYVIS
CALIF PUBLIC UTILITIES COMMISSION MILLER STARR REGALIA
LEGAL DIVISION 5TH FLOOR
ROOM 5039 1331 NORTH CALIFORNIA BLVD
505 VAN NESS AVENUE WALNUT CREEK, CA 94596
SAN FRANCISCO, CA 94102-3214 FOR: FRIESEN FOCUS, FERNANDEZ TRUST,
FOR: DRA JOSEPH FERNANDEZ & JOAN FERNANDEZ
MRW & ASSOCIATES, LLC GREGORY M. MURPHY
EMAIL ONLY BURKE WILLIAMS AND SORENSEN, LLP
EMAIL ONLY, CA 00000 444 SOUTH FLOWER STREET, SUITE 2400
FOR: MRW & ASSOCIATES INC. LOS ANGELES, CA 90071
CASE ADMINISTRATION JANE LEE COLE, ESQ.
SOUTHERN CALIFORNIA EDISON COMPANY SOUTHERN CALIFORNIA EDISON COMPANY
LAW DEPARTMENT, ROOM 370 PO BOX 800 / 2244 WALNUT GROVE AVENUE
2244 WALNUT GROVE AVENUE, ROOM 370 ROSEMEAD, CA 91770
ROSEMEAD, CA 91770 FOR: SOUTHERN CALIFORNIA EDISON
FOR: SOUTHERN CALFORNIA EDISON COMPANY
DAVID KATES DONALD C. LIDDELL, PC
THE NEVADA HYDRO COMPANY DOUGLASS & LIDDELL
2416 CADES WAY 2928 2ND AVENUE
VISTA, CA 92083 SAN DIEGO, CA 92103
FOR: THE NEVADA HYDRO COMPANY FOR: DOUGLAS & LIDDELL
KEVIN O'BEIRNE JOHN BROWN
SAN DIEGO GAS & ELECTRIC COMPANY BEST BEST & KRIEGER
8330 CENTURY PARK COURT, CP32D 3750 UNIVERSITY AVENUE, SUITE 400
SAN DIEGO, CA 92123 RIVERSIDE, CA 92502
FOR: SAN DIEGO GAS & ELECTRIC COMPANY
LINDA RIDENOUR RICHARD LEE
33628 BRAND AVE 555 BIRCH STREET
LAKE ELSINORE, CA 92530 LAKE ELSINORE, CA 92530
FOR: LAKE ELSINORE HISTORICAL SOCIETY
GAYLE LARSSON ANNE STRUM
RANCHO CAPISTRANO 23863 NUTWOOD WAY
17721 RODEO ROAD MURRIETA, CA 92562
LAKE ELSINORE, CA 92530-7527
Information Only
Page 2 of 5
CPUC - Service Lists - A0902012
7/6/2010
http://docs.cpuc.ca.gov/published/service_lists/A0902012_78210.htm

Page 15
ANNIE & ALAN OMENS BOB & MARY BOEM
41955 AVENIDA LA CRESTA 42890 AVENIDA PERRIS
MURRIETA, CA 92562 MURRIETA, CA 92562
FOR: PROTEST LETTER
CHRISTINE A. GIRALDIN DICK & JAN HARRIS
40080 VIA CABALLOS 38557 VIA MAJORCA
MURRIETA, CA 92562 MURRIETA, CA 92562
ED & GERT LA FASO HAROLD RAMSER
43200 TENAJA RD. 39100 AVENIDA LA CRESTA
MURRIETA, CA 92562 MURRIETA, CA 92562
JACK R. WARREN JERRY FOSTER
21285 AVENIDA INSOOK 20047 CORTE FLORENIA
MURRIETA, CA 92562 MURRIETA, CA 92562
KEITH E. CARD KELLY SMITH
19050 ALBORADO 39100 VISTA DEL BOSQUE
MURRIETA, CA 92562 MURRIETA, CA 92562
LORI SWINGLE MRS. CHARLES T. FEENEY
38000 VIA BAYA 38835 AVENIDA LA CRESTA
MURRIETA, CA 92562 MURRIETA, CA 92562
FOR: LCPOA MEMBER
PAUL S. NASH ROBERT BANOCZI
20855 AVENIDA CASTILLA 38275 VIA HUERTA
MURRIETA, CA 92562 MURRIETA, CA 92562
STEVE FULGHAM SUSAN DAVIS
LCPOA 37961 CALLE DE LOBO
39100 VISTA DEL BOSQUE MURRIETA, CA 92562
MURRIETA, CA 92562
TALLY HOFFMAN WILLIAM C. THRALLS
43455 CORONA CALA CAMINO 38351 VIA MAJORCA
MURRIETTA, CA 92562 MURRIETA, CA 92562
BOB WINN HARRIET MICHLIN
21410 AVENIDA DE ARBOLES 38632 VIA MAJORCA
MURRIETA, CA 92562-9102 MURRIETA, CA 92562-9316
YVONNE BANER JOHN LLOYD
43434 BUISNESS PARK DRIVE 23164 CANNERY RD.
TEMECULA, CA 92590 WILDOMAR, CA 92595
MICHAEL & JOANN JUHA GARRY BROWN
PO BOX 1024 EXECUTIVE DIRECTOR & COASTKEEPER
WILDOMAR, CA 92595 ORANGE COUNTY COASTKEEPER
3151 AIRWAY AVE. SUITE F-110
COSTA MESA, CA 92626
PHYLLIS TAYLOR LINDA COPPOLA
27325 VIA CAPRI 1311 PAJERO DRIVE
SAN JUAN CAPISTRANO, CA 92675 CORONA, CA
92882
JACQUELINE AYER LOULENA A. MILES
2010 WEST AVENUE K, NO. 701 ADAMS BROADWELL JOSEPH & CARDOZO
LANCASTER, CA 93536 601 GATEWAY BLVD., SUITE 1000
Page 3 of 5
CPUC - Service Lists - A0902012
7/6/2010
http://docs.cpuc.ca.gov/published/service_lists/A0902012_78210.htm

Page 16
FOR: JACQUELINE AYER SOUTH SAN FRANCISCO, CA 94080
MARC D. JOSEPH KASIA SMOLEN
ADAMS BROADWELL JOSEPH & CARDOZO PACIFIC GAS AND ELECTRIC COMPANY
601 GATEWAY BLVD. STE 1000 77 BEALE STREET, B10A
SOUTH SAN FRANCISCO, CA 94080 SAN FRANCISCO, CA 94105
FOR: PACIFIC GAS AND ELECTRIC COMPANY
CASSANDRA SWEET JULIE L. FIEBER
DOW JONES NEWSWIRES FOLGER LEVIN & KAHN LLP
201 CALIFORNIA ST., 13TH FLOOR 275 BATTERY STREET, 23RD FLOOR
SAN FRANCISCO, CA 94111 SAN FRANCISCO, CA 94111
HILARY CORRIGAN CASE COORDINATION
CALIFORNIA ENERGY MARKETS PACIFIC GAS AND ELECTRIC COMPANY
425 DIVISADERO ST. SUITE 303 PO BOX 770000; MC B9A
SAN FRANCISCO, CA 94117-2242 SAN FRANCISCO, CA 94177
ARTHUR F. COON PHILIPPE AUCLAIR
MILLER, STAR & REGALIA 11 RUSSELL COURT
1331 NO. CALIFORNIA BLVD., FIFTH FLOOR WALNUT CREEK, CA 94598
WALNUT CREEK, CA 94596
FOR: FRIESEN FOCUS LLC, THE FERNANDEZ
TRUST AND JOSEPH AND JOAN FERNANDEZ
KEVIN WOODRUFF
WOODRUFF EXPERT SERVICES, INC.
1100 K STREET, SUITE 204
SACRAMENTO, CA 95814
FOR: WOODRUFF EXPERT SERVICES, INC.
ANDREW CAMPBELL ANGELA K. MINKIN
CALIF PUBLIC UTILITIES COMMISSION CALIF PUBLIC UTILITIES COMMISSION
EXECUTIVE DIVISION DIVISION OF ADMINISTRATIVE LAW JUDGES
ROOM 5203 ROOM 5017
505 VAN NESS AVENUE 505 VAN NESS AVENUE
SAN FRANCISCO, CA 94102-3214 SAN FRANCISCO, CA 94102-3214
BILLIE C. BLANCHARD CHLOE LUKINS
CALIF PUBLIC UTILITIES COMMISSION CALIF PUBLIC UTILITIES COMMISSION
ENERGY DIVISION ELECTRICITY PLANNING & POLICY BRANCH
AREA 4-A
ROOM 4101
505 VAN NESS AVENUE 505 VAN NESS AVENUE
SAN FRANCISCO, CA 94102-3214 SAN FRANCISCO, CA 94102-3214
JENSEN UCHIDA JOSEPH A. ABHULIMEN
CALIF PUBLIC UTILITIES COMMISSION CALIF PUBLIC UTILITIES COMMISSION
ENERGY DIVISION ELECTRICITY PLANNING & POLICY BRANCH
AREA 4-A
ROOM 4209
505 VAN NESS AVENUE 505 VAN NESS AVENUE
SAN FRANCISCO, CA 94102-3214 SAN FRANCISCO, CA 94102-3214
MICHAEL WHEELER MICHAEL YEO
CALIF PUBLIC UTILITIES COMMISSION CALIF PUBLIC UTILITIES COMMISSION
EXECUTIVE DIVISION ELECTRICITY PLANNING & POLICY BRANCH
ROOM 5206 ROOM 4103
505 VAN NESS AVENUE 505 VAN NESS AVENUE
SAN FRANCISCO, CA 94102-3214 SAN FRANCISCO, CA 94102-3214
NICHOLAS SHER PAMELA NATALONI
State Service
Page 4 of 5
CPUC - Service Lists - A0902012
7/6/2010
http://docs.cpuc.ca.gov/published/service_lists/A0902012_78210.htm

Page 17
CALIF PUBLIC UTILITIES COMMISSION CALIF PUBLIC UTILITIES COMMISSION
LEGAL DIVISION LEGAL DIVISION
ROOM 4007 ROOM 5124
505 VAN NESS AVENUE 505 VAN NESS AVENUE
SAN FRANCISCO, CA 94102-3214 SAN FRANCISCO, CA 94102-3214
RACHELLE B. CHONG ROBERT ELLIOTT
CALIF PUBLIC UTILITIES COMMISSION CALIF PUBLIC UTILITIES COMMISSION
EXECUTIVE DIVISION ENERGY DIVISION
ROOM 5205 AREA 4-A
505 VAN NESS AVENUE 505 VAN NESS AVENUE
SAN FRANCISCO, CA 94102-3214 SAN FRANCISCO, CA 94102-3214
TRACI BONE FRITTS GOLDEN
CALIF PUBLIC UTILITIES COMMISSION ASPEN ENVIRONMENTAL GROUP
LEGAL DIVISION 235 MONTGOMERY STREET, SUITE 935
ROOM 5027 SAN FRANCISCO, CA 94104
505 VAN NESS AVENUE
SAN FRANCISCO, CA 94102-3214
MARISA MITCHELL SUSAN V. LEE
ENVIRONMENTAL SCIENTIST ASPEN ENVIRONMENTAL GROUP
ASPEN ENVIRONMENTAL GROUP 235 MONTGOMERY STREET, ROOM 935
235 MONTGOMERY STREET, SUITE 935 SAN FRANCISCO, CA 94104
SAN FRANCISCO, CA 94104
CLARE LAUFENBERG JUDY GRAU
CALIFORNIA ENERGY COMMISSION CALIFORNIA ENERGY COMMISSION
1516 NINTH STREET, MS 46 1516 NINTH STREET MS-46
SACRAMENTO, CA 95814 SACRAMENTO, CA 95814-5512
FOR: CALIFORNIA ENERGY COMMISSION
TOP OF PAGE
BACK TO INDEX OF SERVICE LISTS
Page 5 of 5
CPUC - Service Lists - A0902012
7/6/2010
http://docs.cpuc.ca.gov/published/service_lists/A0902012_78210.htm